The New Build – Part 4

6Part 3 of the new build left us having signed the contracts in December 2013. Now we just sit back and watch the magic happen…or so we thought. Of course a lot of builders and people in construction take a well deserved break over the Christmas and New Year period and there were also permits still in the process so it was anticipated that work would commence (with demolition of the existing home) towards late February/early March 2014. What wasn’t anticipated was the local city council and the delays associated with obtaining a demolition permit to commence the work, closely followed by other delays in getting things signed off so that work could begin. OK, so these things can take time but as the months went by with no visible progress I did start to get concerned. Fortunately the agent put up with my regular calls to see what was going on and reassured me that things were progressing in order to enable works to commence. I know I’m not the only person to sometimes be a touch cynical about what real estate agents tell you so by the time July of 2014 came around I was ready to start building the place myself. You can imagine my relief when I was informed that demolition was commencing and things were starting to move…hooray! It was a useful lesson for me to learn regarding red-tape and associated paperwork and also that when it’s in a larger development you really don’t have much (if any) influence on the speed of the project happening. In August of 2014 the existing house on the block was demolished and work officially commence on-site September 1st 2014, 9 months after we signed on to the project.

By this stage I had started on my Renovation Rescue which had, in part, stemmed from the fact that the new build was taking so long and I was gagging to have another project on the go. Knowing that it would still take considerable time for the construction to be completed I was happy to have the renovation to go on with. Meanwhile back at the building site, temporary fencing, portable toilets, and a site office were initially set up. Then site preparation work involved the removal of existing vegetation from the site. The first stage of construction works on the project were the ‘civil works’. At this stage, all the services were run into the new complex with a deep service trench dug through the common area and the various services including power, gas, water, and telecoms laid in the service trench. Large amounts of rock were encountered during this process, which required special rock breaking machinery to be used which you can see in the attached photos.

Finally though, progress had started. I picked up my paintbrush and went back to the renovation in the hope that now progress would speed up, it certainly did!

This slideshow requires JavaScript.

Advertisement

Join in the discussion here!

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s